Careys

St John's - Manchester Goods Yard

Client

Careys

Completed

2020

Result

Saved up to 24hrs per pour, 0 burst anchors over 95 pours

Live concrete strength measurements and AI-enabled predictions help Careys strike post-tensioned slabs up to 24hrs sooner at Manchester Goods Yard, part of the £1bn St John’s Quarter master plan.

Background

Manchester Goods Yard is the creative and professional hub of the £1bn St John’s quarter development with 30,000m2 of floor space, across nine floors, dedicated to offices, co-working spaces and retail; ‘providing a place for modern industry to thrive’.

Careys were subcontracted to Leandlease to construct the frame which featured a PT slab design.

The first and second steel strand tensions were the critical path activities and could only commence once the strength had exceeded 10MPa and 25MPa, respectively. Precise awareness of the concrete strength development was, therefore, critical to the swift progression of each pour cycle.

Tensioning strands is also a high-risk activity that can lead to burst anchors, cracked concrete and, worse, safety issues if performed too early. Therefore, the accuracy of the concrete strength measurements was paramount.

The Solution

Careys chose Converge to supply digital concrete strength monitoring, having formed a strong relationship working on over 10 projects together, since 2017.

The Mesh sensors and wireless network were easily set up then, for 11 months and 97 concrete pours, reliably collected and wirelessly transmitted data, every 20 minutes, without fail. The 6-month battery life of the Nodes, rugged design and 50+ meter wireless range meant that managing the system during construction was simple.

Using live strength data and AI-enabled predictions, the project team could plan and execute tensioning and striking ahead of up to 24hrs ahead of schedule for every pour.

The accurate, temperature-sensitive calculations meant that Careys could tension and strike slabs all year round, without risking burst anchors due to strength overestimates.

Value Delivered

Saved up to 24hrs per pour

Using ConcreteDNA, Careys could schedule and execute tensioning and striking of every slab pour up to 24hrs sooner than if they had used cubes.

Improved quality and safety

In-situ, temperature-sensitive, strength calculations are accurate regardless of the weather conditions. Year-round, Careys could tension slabs, confident that anchors would not burst; reducing the risk of compromising the quality of the slabs whilst safeguarding those on site. The project was without incident over 30,000m^2 of concrete poured.

Eliminated reliance on site cubes

ConcreteDNA automated concrete testing; reducing the man-hours invested in preparing, curing and crushing cubes. Delays caused by low-cube strengths resulting from poor cube preparation were eliminated and the project team could focus on managing the project rather than chasing cube results.

“The ability to access accurate, real-time data has been invaluable to us at St John's, as it eliminates our reliance on traditional third-party/site cube crushing and we have found we have gained from 4-24 hours on each pour. This allows us to plan our site works to a much tighter programme with obvious cost savings.”
Colm Farrell
Project Engineer, Careys

Similar case studies